S278 Works Edge Lane, Alford Street Housing

Key features
  • CLIENT: Fairtree Homes
  • PROJECT: S278 Works Edge Lane, Alford Street Housing
  • AREA APPROXIMATELY: 200m²
  • PLANT USED: 350 Planer, 80 Roller, Roller Breakers, Trackair, Kerb Lifter, Twin Tool Compressor

Working with Fairtree Homes for AMEY and Liverpool City Council Re Surf completed the off street car parking area for the residents on Alford Street.

These works included civil works with Re Surf having to remove all current surfaces including the MOT, edgings and kerbs had to be completely reinstalled.

Firstly, Resurf excavated the full site and removed all materials to be recycled. Laying the new MOT ourselves and fitting new kerbs in to an excellent standard.

We then completed the surfacing of Binder and Surface course to the car park area ready for the white liners to mark-up perfectly levelled asphalt.

Once we completed the car park, we returned to complete the footpath outside the residents under a section 50 road closure and chapter 8 traffic management to ensure the safety of both our employees and the general public.